x
Send Your Inquiry Today
Quick Quote

Ukraine Kryvyi Kamen Quarry Wireless Surveillance Transmission Project Case

You are reading is a real case study of a WIFI coverage project:

A Quarry Video Monitoring Wireless Transmission Solution Based on COMFAST Wireless Bridges

 

Kryvyi Kamen Quarry Wireless Surveillance Transmission Project

In large-scale quarry operations, stable video surveillance is no longer just a security requirement. It is also an important part of daily production management, vehicle dispatching, risk control, and site coordination. Compared with ordinary commercial environments, a quarry presents far greater challenges for network deployment, including long transmission distances, uneven terrain, heavy dust, strong winds, moving stockpiles, and constant heavy-vehicle activity.

For this reason, the wireless surveillance transmission system used in a quarry must be designed with far more care than a standard network project. It is not enough to simply install devices and make the link work. The real value lies in how the engineering team evaluates the site, predicts long-term changes, chooses the right mounting points, protects equipment in harsh outdoor conditions, and ensures that the entire system remains stable over time.

 

1. Project Implementation Team Introduction

Ukraine Wireless coverage solution

We are a professional WIFI engineering implementation team that has been serving industrial wireless communication scenarios across Eastern Europe for many years, and we regularly undertake various wireless coverage and wireless transmission projects for mines, quarries, storage parks, ports, factories, campuses, hotels, scenic areas, and large-scale industrial parks.
In the local Ukrainian market, we are especially skilled in wireless video surveillance backhaul, long-distance point-to-point / point-to-multipoint bridging, industrial network stability optimization, and integrated weak-current system installation and delivery in complex environments.

Over the years, we have continuously used COMFAST brand equipment in a large number of projects, especially in video monitoring wireless backhaul, inter-zone link connection, and transmission stability improvement in complex obstacle environments, where we have accumulated very mature experience.
For COMFAST wireless bridge products, we are not only familiar with their basic deployment methods, but also highly experienced in tuning details and avoiding common mistakes in complex environments such as strong winds, dust, elevation differences, electromagnetic interference, long-distance open-air links, and restricted construction conditions.

In this project, we selected the following COMFAST device models:

  • CF-E312A V2: Wireless bridge, 5.8G transmission, used for surveillance WIFI transmission
  • CF-E319A V2: Wireless bridge, 5.8G transmission, used for surveillance WIFI transmission
  • CF-GF105: 100M core gateway
  • CF-SF180P: 8-port 100M POE switch

COMFAST CF-E312A V2

This device combination is highly suitable for a quarry environment characterized by large area coverage, difficult cabling, scattered monitoring points, and harsh construction conditions. Based on our long-term field experience, we successfully completed the full delivery process of this project, from site survey, solution design, and device selection to installation, link optimization, and final acceptance.

2. Project Background

This project is located in an open-pit quarry in central Ukraine, and we named it:

Kryvyi Kamen Quarry Wireless Surveillance Transmission Project

This quarry is mainly responsible for stone extraction, crushing, temporary stockyard transfer, and truck loading operations. The site covers a large area, with obvious terrain undulation, and there is a certain distance between the operating zones and the management area.
The customer had already deployed some surveillance cameras before, but because the construction was carried out in different phases over time, the surveillance system had long suffered from the following problems:

  • Some cameras could not transmit video back stably
  • Some monitoring points were too far away for network cable deployment
  • Quarry roads are constantly crushed by heavy transport vehicles, making repeated trenching unsuitable
  • Heavy dust and strong wind caused high failure rates for outdoor equipment
  • The control room could not view multiple key operation areas in real time
  • There were surveillance blind spots in the night loading area, crushing area, and weighbridge area
  • Temporary construction cabling was messy, making later maintenance extremely difficult

The customer’s core requirement was very clear:
They wanted to build a stable, clear, low-maintenance wireless surveillance transmission system suitable for a quarry environment, so that the images from scattered cameras in different operation areas could be transmitted back to the central security monitoring room for all-weather visual management.

Ukraine Wireless coverage solution 1

3. Customer Pain Points and Actual Requirements

After our first round of on-site communication and survey, the customer’s requirements were mainly focused on the following points:

3.1. Key areas had to be included in the surveillance coverage

The customer required at least the following areas to be covered:

  • Quarry pit edge operation area
  • Stone crushing and processing area
  • Finished material stockyard
  • Main road for loaders and transport vehicles
  • Weighbridge area
  • Entrance security booth
  • Diesel equipment parking area

3.2. Minimize trenching and underground cabling

The quarry surface environment is harsh, with frequent movement of heavy trucks, excavators, and loaders.
If traditional fiber or network cabling were used across a large area, the following problems would easily arise later:

  • Conduits being crushed
  • Difficult road surface repair
  • Cables being damaged by vehicle operations
  • Continuously increasing maintenance cost

3.3. Surveillance video had to be stable, with no frequent stuttering

The quarry management team especially emphasized that the video in the weighbridge area, crushing area, and entrance security post had to be continuously stable, without frequent disconnections, black screens, or excessive delay.

3.4. The system structure had to be clear and easy to expand later

The customer was not only focused on current demand, but also hoped that when more cameras were added in the future, the system could be expanded based on the existing structure instead of being rebuilt from scratch.

4. On-Site Survey and Problem Investigation Process

Ukraine Wireless coverage solution 2

A quarry project is different from an ordinary park or campus project. What really determines success is not the paper specification, but whether the site survey is done carefully enough.
After arriving on site, our team did not rush into producing a solution. Instead, we first carried out a systematic investigation and link analysis.

4.1. The terrain problem was more complicated than expected

The quarry is a typical terrain with large elevation differences, and some areas had:

  • Quarry slope obstruction
  • Obstruction from steel structures around crushing equipment
  • Newly increased stockpile heights creating fresh obstacles
  • Line-of-sight limitations between the loading platform and the weighbridge area

This meant that not all camera points could directly establish a wireless link with the monitoring room, and a layered relay design was necessary.

4.2. Dust had a major impact on equipment installation locations

In the crushing area and around the stockyard, fine dust remained in the air for a long time.
If equipment was installed too low, or directly facing the discharge port or crushing machine output direction, then after long-term operation, dust would quickly accumulate on the equipment surface, interface positions, and power boxes.
This would not only affect heat dissipation, but also increase connector oxidation and maintenance frequency.

4.3. The original power supply points were not standardized

The customer had previously reserved camera power points in some areas, but the way the power was brought out was not uniform, including:

  • Insufficient waterproofing of power boxes
  • Strong current and weak current running together
  • Large voltage fluctuation
  • No standard weak-current box at some pole locations

Therefore, we could not only consider the wireless link. We also had to consider the power supply and switch access method at the same time.

4.4. Metal equipment and vehicles could cause short-term obstruction

Large-tonnage vehicles, loaders, temporary stockpiles, and the steel structure of the crushing equipment could all create certain impacts on the 5.8G link.
Although 5.8G has good anti-interference performance, it has higher line-of-sight requirements, so the installation height and angle had to be extremely precise.

4.5. Wind conditions placed higher demands on poles and alignment accuracy

The project site is open and often experiences strong crosswinds.
Once a wireless bridge is installed on a bracket with insufficient structural strength, even a slight displacement later can cause:

  • Link signal drop
  • Unstable throughput
  • Higher packet loss
  • Surveillance image interruptions

Therefore, this project required more effort in installation structure reinforcement than an ordinary industrial park project.

5. Project Solution Design Approach

Based on the actual site conditions, we ultimately adopted a solution of centralized management in the core monitoring room + multi-segment 5.8G wireless bridge backhaul + zoned POE switch access.

The design principles were as follows:

  • Centralize all surveillance data in the core monitoring room
  • Use wireless bridges in key areas to reduce long-distance wired construction
  • Connect nearby cameras through POE switches
  • Use relay design to bypass obstacles in areas that cannot transmit directly
  • Divide each area into independent sections for clearer future maintenance
  • Give priority to line-of-sight and installation stability at all key points

6. Project Equipment List

The actual core equipment used in this project is as follows:

Core network equipment

  • CF-GF105 100M core gateway × 1
  • CF-SF180P 8-port 100M POE switch × 4

Wireless transmission equipment

  • CF-E312A V2 5.8G wireless bridge × 4 units
  • CF-E319A V2 5.8G wireless bridge × 6 units
CF-E319A V2
900Mbps Project Outdoor CPE

Other auxiliary materials and construction materials

  • Outdoor waterproof weak-current boxes
  • Outdoor pole-mount brackets and reinforcement parts
  • Galvanized poles / pole-mount installation components
  • Outdoor waterproof Cat5e network cables
  • Lightning protection modules and power protection devices
  • Cable ties, wire clips, corrugated pipe, PVC conduit
  • Grounding materials
  • Camera mounting bases and waterproof connectors
  • Labeling system and port identification materials

7. Why These COMFAST Devices Were Chosen

7.1. Reasons for using CF-E312A V2

This model is suitable for taking on stable bridging tasks at some short-to-medium distance key points.
In this project, we mainly used it for:

  • Stable bridging between the management area and nearby operation areas
  • Direct line-of-sight links with good signal conditions
  • Positions requiring high installation flexibility

The reasons for choosing it were:

  • The 5.8G band is suitable for surveillance wireless transmission
  • Better resistance to common 2.4G interference
  • Relatively flexible installation and deployment
  • Able to meet the bandwidth requirements for video backhaul in key quarry areas
  • With proper line-of-sight and installation height, it provides good stability

7.2. Reasons for using CF-E319A V2

This model took on more important long-distance or backbone link tasks in the project, mainly used for:

  • Backhaul from the quarry pit edge to relay points
  • Backbone links from relay points back to the management area
  • Key return links in the crushing area and stockyard direction

The reasons for choosing it were:

  • Better suited to building outdoor links in scenarios like a quarry
  • Mature application experience in point-to-point transmission
  • More suitable for backbone backhaul and future redundancy planning
  • Stable performance in open environments, suitable for continuous surveillance video transmission

7.3. Reasons for using CF-GF105

The customer’s surveillance system scale was not highly complex. At this stage, the main need was surveillance transmission rather than a large enterprise office network.
Therefore, we did not overbuild the configuration, and selected the CF-GF105 100M core gateway as the core output and unified network management device.

Its advantages are:

  • Meets the current surveillance network aggregation requirements
  • Simple structure, easy to manage
  • Matches the overall 100M transmission system
  • Reasonable cost and easy later maintenance

7.4. Reasons for using CF-SF180P

In quarry projects, front-end devices are scattered, and many camera installation points are not suitable for deploying separate power devices.
The CF-SF180P 8-port 100M POE switch effectively solves the problem of centralized access and power supply for front-end cameras and wireless bridges.

The main reasons for choosing it are:

  • Can provide POE power to front-end cameras
  • Reduces the number of independent power adapters on site
  • Centralized equipment access makes maintenance easier
  • Suitable for deployment in small zoned aggregation boxes
  • Very practical for a quarry scenario with scattered points

COMFAST CF-SF180P 4

8. Project Network Topology Diagram

Below is the simplified topology diagram finally implemented for this project:

Ukraine Wireless coverage solution topo

Note: In the actual construction, some links were adjusted according to pole positions, height differences, and on-site obstructions. The diagram above is the logical topology after final delivery.

9. Detailed Networking Explanation by Area

9.1. Core monitoring room area

The monitoring room is located in the management office area and is the data aggregation center of the whole system.
The following equipment was deployed here:

  • CF-GF105 100M core gateway
  • Surveillance recording host / NVR
  • Display terminal
  • Main-station wireless bridge access end

The most important requirements in this area were:

  • Clear network structure
  • Unified access for all outdoor links
  • Easy fault locating
  • Convenient future remote viewing and recording management

9.2. Weighbridge and entrance security area

This was one of the most important areas for the customer.
Because transport vehicles enter and exit frequently, weighbridge disputes, loading record verification, and night duty management all rely on video.

Our approach was:

  • Establish an independent wireless link to the weighbridge area through CF-E312A V2
  • Deploy CF-SF180P inside the weak-current box in the weighbridge area
  • Connect the weighbridge camera, entrance camera, and road capture camera

The advantages of this approach were:

  • Independent link for better stability in key areas
  • Centralized power supply through the switch simplifies maintenance
  • Unified management of entrance and weighbridge surveillance

9.3. Crushing area and stockyard

The crushing area had the heaviest dust, the most machinery, and the most complex structural obstruction.
We did not install the wireless bridge directly on the structure of the main equipment with the strongest vibration. Instead, we:

  • Chose stable side steel structure points or independent poles for installation
  • Kept the equipment height above the main dust spray surface
  • Avoided the main output direction of the crusher
  • Carried out fine alignment of the bridge direction

At the same time, we deployed CF-SF180P in this area to connect:

  • Crusher operation monitoring
  • Stockyard monitoring
  • Loading position monitoring

4. Quarry pit edge operation area

This was the most difficult area to handle.
On the one hand, the distance was long; on the other hand, there were elevation differences and slope obstructions, and the camera positions could also change with the phased quarrying progress.

Our design approach was:

  • Do not force a direct one-hop link from the monitoring room
  • First use a relay point to extend the backbone link to a high point near the quarry pit
  • Then use CF-E312A V2 / CF-E319A V2 for segmented bridging
  • Set up a small aggregation box at the edge of the operation area, where CF-SF180P connected nearby cameras

This not only reduced the burden on a single link section, but also made later adjustment more flexible.

10. Actual Problems Encountered During Construction and Solutions

Ukraine Wireless coverage solution 3

What truly reflects professional ability in a quarry project is not the equipment list, but how problems are handled during construction.
The typical issues we encountered in this project were as follows:

Problem 1: The originally planned link was blocked by a newly added stockpile

During the second recheck, we found that the originally good line-of-sight direction had become partially blocked at a low level because of a newly added temporary stone stockyard.

Solution:
  • Recalculated the effective line of sight
  • Increased the installation height on one side
  • Fine-tuned the relay point position
  • Changed one direct link into a two-segment transmission design

Experience summary:
A quarry is a dynamic scenario. Stockyard locations change, vehicle routes change, and solution design must not rely on only one site visit. Future changes must be considered in advance.

Problem 2: Strong crosswind at one pole position caused link fluctuation

One relay point was installed on a relatively high pole position. The actual wind on site was stronger than expected, and after the first installation, testing showed slight signal fluctuation.

Solution:
  • Replaced the mount with a more stable pole-fixing assembly
  • Reinforced the support points
  • Optimized the bridge fixing angle
  • Re-aligned the direction precisely again

Experience summary:
In open quarry areas, the mechanical strength and installation firmness are just as important as wireless parameters.

Problem 3: Heavy dust in the crushing area required stronger interface protection

The dust environment in the crushing area was extremely severe, and ordinary installation would easily lead to dust accumulation at the network cable connectors and waterproof box positions.

Solution:
  • Raised the height of the weak-current box
  • Unified the cable routing and created downward drip loops
  • Strengthened connector protection
  • Installed equipment in directions that avoided facing the dust directly

Experience summary:
In an industrial site, the project is not finished just by mounting the equipment. Dust protection, waterproofing, heat dissipation, and future maintenance convenience must all be considered in advance.

Problem 4: Some camera power supply points were not standardized

The customer’s originally reserved power points were not suitable for direct use.

Solution:
  • Reorganized the internal layout of front-end weak-current boxes
  • Used CF-SF180P to provide unified POE power for cameras
  • Separated strong current and weak current
  • Re-numbered and labeled all ports

Experience summary:
Disorganized front-end power supply is one of the root causes of frequent later surveillance system failures, and must be standardized in one step.

Problem 5: The customer was concerned that a wireless solution would be less stable than a wired one

This is a common concern among industrial customers. At the beginning, the customer worried that wireless transmission might “look convenient, but not remain stable in the long term.”

Solution:

We did not rely only on verbal explanation. Instead, we completed the following on site:

  • Single-link stability testing
  • Simultaneous multi-channel video backhaul testing
  • Daytime and nighttime continuous observation
  • Recording sampling inspection in key areas
  • Packet loss and latency performance verification

We used actual performance to confirm to the customer that:
In a quarry environment like this, a properly designed wireless bridging solution is more suitable for long-term operation than blindly laying long-distance cables.

11. Installation and Commissioning Details

Ukraine Wireless coverage solution 4

To ensure that the system would truly remain stable, we insisted on the following standards during implementation:

11.1. All wireless bridges had to be installed based on line-of-sight first, then pole position

We did not install equipment simply where it was convenient. Instead, we first ensured:

  • Clear line of sight
  • Avoidance of large steel structure obstructions
  • Avoidance of areas likely to become future stockpiles
  • Keeping away from high-vibration machinery as much as possible

11.2. Unified numbering and cable routing for all front-end boxes

The switches, cameras, bridges, power supply, and uplink links in each area were clearly labeled for easy later customer maintenance.

11.3. Bridge direction was fine-tuned, not roughly installed

Many teams install wireless bridges only to the point where “they can connect.” But we insisted on tuning the links to a more stable condition, including:

  • Fine azimuth adjustment
  • Elevation angle optimization
  • Link stability observation
  • Re-testing at different times of day

11.4. Power supply, grounding, and protection were completed together

For long-term outdoor operation in a quarry, it is not enough to only see whether the network is connected. We also had to consider:

  • Waterproofing
  • Dust protection
  • Anti-loosening measures
  • Basic lightning protection
  • Power stability

11.5. Expansion capability was reserved

We reserved spare ports on some CF-SF180P switches so that the customer could add cameras later without major changes to the architecture.

12. Project Acceptance Process

Ukraine Wireless coverage solution 5

After the project was completed, we carried out a systematic acceptance process together with the customer. The main acceptance items included:

12.1. Real-time video preview acceptance

Each camera was checked one by one to confirm:

  • Clear image
  • No obvious stuttering
  • No large-scale frame loss
  • Continuous and stable image in key areas

12.2. Recording playback acceptance

We sampled recordings from the weighbridge area, crushing area, entrance area, and quarry pit edge area to confirm that recording integrity met management requirements.

12.3. Link stability acceptance

We continuously observed the wireless bridge links, with special focus on:

  • Whether they disconnected frequently
  • Whether they fluctuated sharply
  • Whether they remained stable during peak operation periods

12.4. Night-time acceptance

Considering the quarry’s night operation needs, we specially arranged night-time image and link rechecking to ensure that the night security team could use the system normally.

12.5. Operation and maintenance handover acceptance

We explained to the customer’s on-site manager:

  • Which devices belonged to the core links
  • Which switches corresponded to which cameras
  • How to quickly determine faults if problems occurred
  • Which nodes should be prioritized when expanding later

13. Positive Feedback from the Customer After Acceptance

After project acceptance was completed, the customer’s management team, security duty personnel, and on-site maintenance staff all gave very positive feedback.

Feedback from the customer’s management team

“This system is much clearer and more organized than the scattered surveillance setup we had before. Especially for the weighbridge, crushing area, and transport road, we can now finally see the real-time video stably, and management efficiency has improved significantly.”

Feedback from security duty personnel

“Some areas used to disconnect frequently, and night shifts were the most troublesome. Now the video in the monitoring room is much smoother, and switching between cameras is more convenient. We feel much more confident during duty.”

Feedback from on-site maintenance staff

“This time your team did things differently from other contractors. You did not just install the equipment and leave. Every cable, every box, and every uplink relationship is organized very clearly, so it is much easier for us to troubleshoot later.”

14. What We Did Differently from Other Engineering Teams

The reason this project was successfully implemented and recognized by the customer was not only the device brand and models, but also the implementation logic.
Compared with many ordinary construction teams, our work in this project had several obvious differences:

14.1. Not an “equipment selling mindset,” but a “site link mindset”

Many teams only know how to select equipment based on specifications, but in a quarry project, what truly determines stability is:

  • Line-of-sight analysis
  • Elevation difference judgment
  • Relay design
  • Pole position selection
  • Installation strength
  • Prediction of future dynamic changes

We first fully understood the on-site link conditions, and only then finalized the equipment and structure.

14.2. Greater emphasis on later maintenance

In many projects, the biggest hidden danger after delivery is not device failure, but that nobody knows which cable goes where.
In this project, we made the labels, numbering, wiring logic, and area division very clear, greatly reducing the difficulty of future maintenance.

14.3. Better understanding of the real problems of industrial sites

A quarry is not an ordinary office building. The biggest enemies are not “insufficient specifications,” but:

  • Dust
  • Wind
  • Vibration
  • Obstruction changes
  • Risk of heavy vehicle crushing
  • Inconvenient on-site construction conditions

Our team’s experience in handling these issues directly determined the final stability of the project.

14.4. Not pursuing superficial complexity, but long-term usability

We did not pile up unnecessary equipment just to make the project look “high-end.” Instead, based on the customer’s actual needs, we used the most suitable COMFAST device combination to achieve:

  • Controlled cost
  • Clear structure
  • Long-term stability
  • Easy expansion

15. Project Summary

The Kryvyi Kamen Quarry Wireless Surveillance Transmission Project is a very typical quarry wireless surveillance backhaul case.
This project once again proved one thing:

For scenarios such as quarries, mines, stockyards, and industrial parks, a properly designed 5.8G wireless bridge transmission solution is often more efficient, more flexible, and more suitable for long-term maintenance than large-scale traditional cabling.

In this project, through the combined application of COMFAST CF-E312A V2, CF-E319A V2, CF-GF105, and CF-SF180P, we successfully helped the customer solve the following key problems:

  • Video backhaul from scattered surveillance points
  • Difficulty in long-distance cabling
  • Dynamic terrain and obstruction issues
  • Disorder in front-end device power supply and access
  • Unstable surveillance system and low management efficiency

The final delivered system achieved:

  • Unified aggregation of surveillance from multiple areas
  • Real-time and stable video return from key areas
  • Clear network structure
  • Convenient future expansion
  • High customer satisfaction

16. Advice to Other Engineering Teams

Practical advice for contractors handling office WiFi coverage projects

If you are also working on WIFI surveillance transmission projects for quarries, mines, or stockyards, I strongly suggest that you pay attention to the following points:

16.1. Never design a solution based only on a map

A quarry is a dynamic environment. You must inspect on site:

  • Elevation differences
  • Stockpile changes
  • Vehicle routes
  • Steel structure obstructions
  • Wind conditions

16.2. In wireless bridge projects, installation quality determines half of the result

Device specifications are only the foundation. What truly affects long-term stability is:

  • Pole firmness
  • Alignment accuracy
  • Waterproof and dustproof treatment
  • Wiring standardization

16.3. Do not make every link a single-hop just for convenience

In complex environments, when one direct hop is impossible or unstable, reasonably adding relay points is often more stable and easier to maintain.

16.4. Switches and front-end boxes must be organized properly

In many projects, later failures are not caused by wireless links, but by messy internal cabling and non-standard power supply inside front-end boxes.

16.5. Quarry projects must leave room for future change

Stockpile locations will change, work areas will change, and camera points will change.
If your solution has no expansion margin, then once the customer changes the site, your system will immediately become passive and difficult to adapt.

 
 
 
 

The successful delivery of the Kryvyi Kamen Quarry Wireless Surveillance Transmission Project once again proved that in complex industrial environments, a well-designed wireless transmission solution can achieve both stability and long-term practical value. For quarry projects in particular, the key is never just the equipment itself, but the complete engineering logic behind site survey, link planning, installation quality, environmental protection, and future expansion.

 
Scroll to Top